A lithium conversion is a charging system project with batteries at the end of it. Plan it in this order.
Step 1: audit what you have
- Alternator make, output and whether the regulator is internal.
- Every charger and solar controller, and whether each has a lithium setting.
- Battery box size and how well it is ventilated and secured.
- Cable sizes and fuses between the bank, the switch and the main loads.
- Take photos. An installer can quote from good photos.
Step 2: set the size
Use your daily amp hour figure. If you have not worked it out, do that first with the sizing tutorial in this section.
Step 3: choose drop in or designed
- Drop in batteries with a built in BMS suit banks up to roughly 400 Ah and boats without big inverter loads.
- A designed system with an external BMS suits large banks, induction cooking and boats where the BMS should control the chargers.
Step 4: decide how the alternator will be protected
This is the part that gets skipped. Either a DC to DC charger from the start battery, or an external regulator with a temperature sensor on the alternator. There is a separate tutorial on this.
Step 5: list the extras
Budget for more than batteries: battery monitor with shunt, main fuse of the right class, new cable and lugs, DC to DC charger or regulator, replacement chargers, and labour. On many boats these add 30 to 60% to the battery price.
Step 6: tell your insurer
Ask what they need before the work starts. Some want the installer's details and the battery's compliance documents.
Step 7: keep or sell the old bank
A healthy AGM battery makes a good start battery. Do not wire old and new chemistries together in the house bank.
The standard to ask for
Ask the installer to work to AS/NZS 3004.2 and to give you a wiring diagram and the charger settings in writing when the job is done.
What usually gets replaced
| Item | Keep or replace | Why |
|---|---|---|
| Batteries | Replace | The point of the job |
| Alternator regulator | Usually replace or add a DC to DC charger | Lithium will pull a standard alternator to full output until it overheats |
| Shore charger | Check the profile | Needs a lithium setting with no equalise stage |
| Solar controller | Check the profile | Most modern ones have a lithium setting |
| Battery monitor | Replace if it only reads volts | Voltage tells you very little on lithium |
| Main fuse | Replace | Lithium can deliver far more fault current. Use a Class T or equivalent |
| Cables | Check size | Higher charge currents need bigger cable |
How long it takes
A drop in swap on a simple boat is a weekend if the parts are on hand. A designed system with an external regulator, new fusing and a monitor is usually several days of work spread over a few weeks, because you will find things behind panels you did not plan for. Do not start the week before a trip.
Mistakes to avoid
- Leaving the starter battery as lithium. Keep a lead acid start battery so the engine and alternator always have something safe to charge.
- Mixing old lead acid and new lithium in one house bank.
- Mounting the bank in the engine bay. Heat shortens its life.
- Skipping the monitor. Without one you are guessing.
- Buying on capacity alone and ignoring the maximum charge and discharge current of the battery.
When to hand it to a marine electrician
If the plan includes an inverter, shore power changes, or a bank above a few hundred amp hours, pay for a design and a sign off. Insurers in Australia increasingly ask who did the work and to what standard. An invoice from a licensed marine electrician is the simplest answer.